Hallamore enlists two 600-U.S.-ton mobile Demag cranes for the Commonwealth Avenue
accelerated bridge construction project
Heavily congested construction sites like the Commonwealth Avenue Bridge spanning the Massachusetts Turnpike in Boston pose a problem for planning agencies. Conventional bridge construction projects can take years to complete and impede the traffic patterns throughout construction, which does not appeal to the public. Alternatively, accelerated bridge construction (ABC) impacts traffic more significantly but for a shorter time.
The Commonwealth Avenue Bridge is a major Boston thoroughfare. Roughly 200,000 people each day rely on the Turnpike and bridge to get to their destinations, which includes nearby Boston University, Boston College and Harvard. With so much riding on the project, the Massachusetts Department of Transportation (Mass DOT) decided on ABC to replace the 53-year-old structure.
ABC condensed the estimated 3-year conventional bridge construction project into two intense, meticulously planned short-lived masterpieces. The MASS DOT contract called for the eastbound bridge lanes to be demolished and replaced in 2017 and then the westbound in 2018.
The prime contractor had just 20 days to complete total reconstruction of the eastbound lanes and chose a 1600-ton (1,450-tonne) class crawler crane for all the heavy lifting. It was positioned and rigged below the bridge on a portion of the Massachusetts Turnpike. While it had the capacity, “crane assembly time hurt the contractor for such a short-duration project and resulted in extra work and expense during mobilization,” comments Gary Spencer, general manager for Hallamore Corporation of Holbrook, Mass.
When it came time to repeat the process in just 15 days for the westbound bridge, lessons learned from the 2017 process had the prime contractor working with Hallamore to devise a lift plan with a shorter crane set-up time. Hallamore’s strategy included using two 600-U.S.-ton (500-tonne) class all terrain cranes – the Demag® AC 500-8 and AC 500-1 – one working on Commonwealth Avenue and the other from the Massachusetts Turnpike. “Using a crawler crane would have been extremely difficult for this phase due to the incline where the crane had to be positioned,” adds Spencer.
A Need for Speed
The monumental task required installing 45 bridge beams with lengths ranging up to 165 ft (50.3 m) and weights up to 66 U.S. tons (60 tonnes). The cranes also placed 214 precast concrete deck panels weighing up to 19,500 lb (8.8 tonnes) and positioned abutment backwall panels weighing up to 59,000 lb (26.8 tonnes) each. “Mass DOT requires a load factor, which, of course, was included while planning the lift,” comments Justin Melvin, territory manager for Empire Crane Company, a Terex Cranes authorized distributor.
While the number of travel lanes was restricted during the planned 15-day construction period, the Mass Turnpike remained opened, which created some congestion for crane positioning. “We knew it was going to be tight, so our 600-U.S.-ton (500-tonne) Demag cranes were the best choice,” says Spencer. Andrew Longacre, regional business manager for Terex Cranes, adds, “The AC 500-8 has a carrier length of just over 56 ft (17 m), making it the most compact eight-axle crane in its class, perfect for accessing congested sites.”
Both cranes were quickly mobilized, along with 12-13 truckloads of counterweight and rigging materials for each crane, to the Commonwealth Avenue Bridge from Hallamore’s Holbrook yard, approximately 25 mi (40.2 km) away. Hallamore has used its AC 500-1 crane for nearly 15 years. “It has been very dependable for us, and that is why we decided to purchase the AC 500-8 (current class model) for this project,” mentions Spencer.
Hallamore purchased the Demag AC 500-8 for this project from Empire Crane, which is based in Syracuse, N.Y. & has branches in Bridgewater, N.J. and Boston, Mass. The Hallamore family and the Lonergan brothers, owners of Empire Crane, have done business together for over 25 years, including multiple crane sales, parts and crane service.
The new crane arrived just weeks before the Commonwealth Avenue Bridge project. Terex Cranes and Empire representatives worked with Hallamore to make sure it was ready for days of intense, round-the-clock lifting. “Crane set-up went flawlessly, so we were confident it was ready for the project,” adds Spencer.
During initial set-up, Spencer and his crane operator noticed some differences between the new crane and the 2003-vintage model. The additional tie-off points on the new AC 500-8 crane were appreciated, since they enhanced safe rigging of the mobile crane.
The new IC-1 Plus control system also caught Spencer’s eyes. “The crane functions are very similar between the two cranes, but the control system on the new crane is touch-screen and a lot easier to operate,” he says. IC-1 Plus is designed to provide the crane’s maximum allowable lifting capacity, based on slewing angle, for main boom operation. “The capacity charts of the AC 500-8 are improved over our older crane,” adds Spencer. “We have another job upcoming where the older AC 500-1 does not offer the capacity to complete, but the AC 500-8 does.”
Working in Combination
The AC 500-1 crane drove into its spot on the Massachusetts Turnpike, and Hallamore’s crew rigged it in-place with full 352,800 lb (160 tonnes) of counterweight in about 4 hours, a fraction of the time it would have taken to fully erect a crawler crane. Due to crane positioning for the lifts, Hallamore’s crew did not need to rig this crane with the sideways superlift (SSL) structure.
The newer AC 500-8 crane was positioned on Commonwealth Avenue, nearby the bridge. The lift plan called for the use of its full 183.7-ft (56-m) telescopic boom to pick the concrete panels. Since operating radius reached 168 ft (51.2 m), crews rigged this crane with its full 396,800-lb (180-tonne) counterweight stack and SSL for additional lifting capacity. “Even with the SSL, we were still hook-ready within 6 hours,” adds Spencer.
During bridge span demolition, the AC 500-1 removed girders and worked its way toward the abutment span by span. In just 36 hours, spans 1 and 2 were completely removed. “In total, Hallamore removed 1,700 U.S. tons (1,542 tonnes) of scrap steel,” says Melvin.
For reconstruction, the AC 500-8 lifted and positioned 8 beams weighing up to 33,200 lb (15 tonnes) using 154.9 ft (46.9 m) of boom length. Based on span location, operating radius was set at either 120 or 128 ft (36.6 or 39 m). The lifts required 17,700 lb (8 tonnes) of rigging and block weight that had to be accounted for, plus the 1.5 times load safety factor. “The heaviest girder lift was positioned with 154.9 ft (46.9 m) of boom at a 120-ft (36.6-m) radius, which gave crews a capacity of 76,500 lb (34.7 tonnes), enough to allow them to complete the lift with safety factor,” comments Longacre.
From Turnpike level, the AC 500-1 worked closer to the spans to make several heavy picks. The heaviest weighed 78,800 lb (35.7 tonnes), giving it a total load weight with rigging and hook block of 96,500 lb (43.8 tonnes). Factoring in the Mass DOT safety requirements, the crane needed to rate at 144,800 lb (65.7 tonnes) to complete the lift. “We handled this load with 106.9 ft (49 m) of boom at a 65-ft (19.8-m) radius, which gave us a 160,300-lb (72.7-tonne) capacity,” says Spencer.
The precast concrete road and light rail deck panels were placed by both Demag cranes. Panel weights for the AC 500-8 crane ranged from 4,100 to 19,500 lb (1.9 to 8.8 tonnes), placed with 183.7 ft (56 m) of boom at a maximum radius of 168 ft (51.2 m). Panel picks for the AC 500-1 were made with 170 ft (51.8 m) of boom at a maximum 157-ft (47.9-m) radius. Once the panels were in place, 680 yd3 (520 m3) of concrete and 580 US tons (526 tonnes) of asphalt finished the process.