Wirtgen technologies in successful operation on Interstate 81

“Using the cold recycling method has the potential to revolutionize how we rehabilitate our aging roads, both in Virginia and nationally,” said the Governor of Virginia, Robert F. McDonnell, expressing his delight with the results of the rehabilitation measures on Interstate 81. Looking to the future, he said: “We expect to continue using these processes, where appropriate, to save money and materials as we rebuild older roads throughout the commonwealth.”

The Wirtgen WR 2400 cold recycler stabilized the existing subgrade material and pre-spread binding agent to a depth of 30 cm

The Wirtgen WR 2400 cold recycler stabilized the existing subgrade material and pre-spread binding agent to a depth of 30 cm

Roads & Bridges magazine and the Asphalt Recycling & Reclaiming Association (ARRA) share the Governor’s opinion. They presented the construction project and the responsible authority – the Virginia Department of Transportation (VDOT) – with the 2012 Recycling Award in the “Cold in-Place” category. The awards recognize top asphalt road recycling projects in North America. Winners are selected based on the amount of recycled pavement material used, cost savings and project challenges.

Cold recycling – leading technology in structural road rehabilitation

One of the major north-south routes in the eastern United States of America runs across the state of Virginia with two lanes in each direction – Interstate I-81. Continuously increasing traffic volumes and the loads imposed by heavy-vehicle traffic had left the pavement surface covered with alligator cracks, wheel ruts and patches where minor repairs had been carried out. In previous years, VDOT had been able to keep traffic up and running by carrying out extensive repair operations. In the spring of 2011, however, a 6-km-long stretch near Staunton on the right-hand truck lane required complete rehabilitation due to structural damage and an inadequate load-bearing capacity. The left-hand passenger car lane, which was subject to lower loads, was to be rehabilitated by cold recycling to a depth of 12 cm. This highly challenging construction project involved the use of as many as three different recycling methods – making this a unique project for the rehabilitation of an interstate in the USA. All the more reason for VDOT to opt for the high-performance cold milling machines, cold recyclers and mobile cold recycling mixing plant from the Wirtgen Group and an entire fleet of Hamm rollers.

The 3800 CR recycled the subgrade in a single pass while adding foamed bitumen to the process

The 3800 CR recycled the subgrade in a single pass while adding foamed bitumen to the process

Rehabilitation: pioneering, economical, resource-efficient

During the rehabilitation of the truck lane, the compact dimensions of the Wirtgen Group machines minimized the disruptions to traffic: vehicles were guided past the job site on the adjacent, left-hand lane, thus maintaining a continuous flow of traffic. W 210 and W 2100 large milling machines removed the entire asphalt material down to a depth of 25 cm in a single pass. The LEVEL PRO levelling system specifically designed by Wirtgen for use in cold milling machines made light work of this difficult task, precisely maintaining the selected milling depths. Trucks seamlessly transported the reclaimed granulated material to the mobile mixing plant KMA 220 for recycling. A Wirtgen WR 2400 cold recycler with a working width of 2.40 m was at the ready for the soil stabilizing operation to be carried out next, which would restore the subgrade to the required bearing capacity. At the same time, the cold recycling mixing plant was busy recycling the reclaimed asphalt material in an “in-plant” process for full reuse. Its mobile mixing design enabled the mixing plant to be set up in the immediate vicinity of the construction site, which not only reduced the distance to be covered by the transport trucks, fuel consumption rates and CO2 emissions, but also resulted in a significant reduction of the overall construction costs. Asphalt pavers placed the material on the stabilized subgrade as a 20-cm-thick layer that was then effectively compacted by tandem rollers from Hamm. Finally, a 5-cm-thick asphalt layer was placed on top.

The high-performance KMA 220 mobile mixing plant set up in the vicinity of the construction site produced high-quality cold mix.

The high-performance KMA 220 mobile mixing plant set up in the vicinity of the construction site produced high-quality cold mix.

The rehabilitation of the left-hand lane was then begun without delay. As it had mostly been used by passenger cars in the past, it required less extensive rehabilitation methods. In a first step, the W 2100 milled off the 5-cm-thick surface course at a gradient of 2%. After pre-spreading 1% pure cement, the Wirtgen 3800 CR cold recycler equipped with a 3.8-m-wide, integrated paving screed gained centre stage for the “in-situ” processing of the traffic lane. It is a major advantage of this process that neither the source material nor the recycled construction material mix require any transport effort. The cold recycler milled off and granulated the damaged asphalt layer down to a depth of 12 cm in a single pass – while the milling and mixing rotor mixed in foamed bitumen, cement and water at the same time. The 3800 CR then paved and pre-compacted the recycled mix by means of the integrated Vögele paving screed. Final compaction was carried out by tandem and rubber-wheeled rollers from Hamm. The rehabilitation work was completed by paving an asphalt course on top of the recycled base.

Hamm tandem and rubber-wheeled rollers quickly and reliably compacted the left-hand lane previously produced in an "in-situ" process

Hamm tandem and rubber-wheeled rollers quickly and reliably compacted the left-hand lane previously produced in an “in-situ” process

Wirtgen technology makes the difference – VDOT is planning another project

Ground-breaking cold recycling technologies from Wirtgen were the key to success in this showcase project: traffic on the I-81 flowed smoothly again after a short construction period – on two roadways with optimal structural integrity for excellent durability, which were processed in an economical, resource-efficient and environmentally-friendly manner, as VDOT Commissioner Greg Whirley emphasized: “Savings on the I-81 in-place pavement recycling project go beyond time, money and materials. The reduced transports for old and new materia
l saved fuel. Safety for drivers and road workers on the project was also increased, because work-zone congestion was reduced. This section of rebuilt pavement also will be stronger from bottom to top, extending its service life and reducing the need for such complex maintenance for many years.”

The outcome: “VDOT next plans to use cold in-place recycling to rebuild a section of U.S 17 in Isle of Wight County in Hampton Roads during the 2012 paving season”, said Governor McDonnell.

source: http://www.wirtgen-group.com/budapest/en/news-media/press-releases/press-releases-detail.2752.php

Newsroom of HeavyQuip Magazine
Newsroom of HeavyQuip Magazinehttps://www.heavyquipmag.com/
HQM is the digital magazine focused on Construction, Earthmoving, Lifting, Mining, Heavy-duty Farm equipment for the global market